From funding to implementation: Is your Rural Health Transformation project ready to launch?

11.17.26 /

Receiving Rural Health Transformation Program (RHTP) funding is an important milestone. But an approved plan is not necessarily an implementation-ready project. The level of planning needed to secure funding can be very different from the level of detail needed to successfully execute the work. As organizations move from application to implementation, that is the time to pause, validate the plan for execution details, and make sure the right people, resources, and processes are in place.

Here are six questions to consider before moving forward.

1. Is your idea ready to become a project?

While an application establishes what you want to accomplish, when you move to implementation, you must determine exactly how you're going to accomplish it.

That means translating your proposed initiative into a detailed project plan that identifies activities, responsibilities, timelines, milestones, dependencies, and decision-making processes.

Take action

Before launching:

  • Define key activities, milestones, and timelines.
  • Assign an owner to each major component of the project.
  • Identify dependencies that could affect your schedule.
  • Determine who needs to be involved in decisions.
  • Establish a process for escalating issues when they arise.

The goal is to make sure everyone understands what needs to happen next and who is responsible for making it happen.

2. Does your project clearly align with RHTP goals?

As implementation begins, it can be easy to become focused on completing activities, meeting deadlines, and spending funds as planned. But those activities still need to advance the outcomes RHTP is intended to support.

Key initiatives for RHTP funding from the federal level include:

  • Building the rural healthcare workforce: Supporting recruitment, training, and retention strategies to strengthen the pipeline of healthcare professionals serving rural communities.
  • Strengthening rural facilities and access: Supporting partnerships, operational improvements, and care-delivery changes that help rural providers maintain essential services and improve access.
  • Advancing innovative care and payment models: Supporting new approaches to delivery and financing designed to improve quality, strengthen primary care, and support sustainable rural healthcare.
  • Expanding community-based and preventive care: Investing in school-based care, mobile services, and other community strategies that improve prevention, address chronic disease, and expand access to care.
  • Modernizing rural healthcare technology: Expanding remote care and data-driven tools to improve coordination and extend healthcare services to rural communities.

Before implementation begins, confirm that your project still has a clear connection to the goals it is intended to advance at every level of the funding trail.

Take action

Write down the RHTP goal or goals your initiative supports. Then define how you will measure whether the project is actually advancing those goals. Throughout implementation, keep asking, “Is what we're doing still helping us achieve the outcome we set out to accomplish?” If the answer changes, it may be time to revisit the plan.

3. Do you have the people and capacity to do the work?

Funding provides resources, but it doesn't automatically create organizational capacity.

Consider who will be responsible for implementing the initiative and whether those people realistically have the time and expertise to take on the work.

You may have much of the expertise needed internally. Other areas may require project management, outside consulting services, additional technology, interoperability between systems, or other specialized support.

Take action

  • Build a resource plan that identifies:
  • Who will lead the initiative.
  • What responsibilities and tasks will be handled internally.
  • Where there are expertise or capacity gaps.
  • What external support may be needed.
  • When those resources need to be available.

Do this before implementation is underway. Discovering a significant resource gap halfway through the project can put the timeline, funding, and outcomes at risk.

4. Are your vendors and dependencies ready?

Many RHTP initiatives will involve multiple organizations (that may or may not have worked together previously), technologies, systems, and stakeholders. Your project's timeline may depend on all of them.

For example, a technology project may require hardware, networking, integrations, vendor resources, other technology suppliers, and support from internal IT teams. And due to the national outreach of the program, some national resources may already be stretched by other RHTP-funded initiatives. A delay in one area can affect several others.

Take action

Map your project's critical dependencies and ask:

  • What has to happen before each phase of work can begin?
  • Which vendors or outside organizations are involved?
  • Have their availability and timelines been confirmed and have contingencies been considered?
  • What internal resources do they depend on?
  • What happens to the project if one component is delayed?
  • Don't build your timeline around assumptions. Validate the dependencies that matter most.

5. What happens when the RHTP funding ends?

Implementation planning shouldn't stop at getting the project up and running.

Consider what it will take to sustain the initiative once the initial year's funding has been spent. That includes ongoing staffing and operating costs as well as assumptions about reimbursement, utilization, future funding, vendor costs, and other factors that affect long-term viability.

Take action

Develop a post-funding scenario before making major commitments.

Ask:

  • What will this cost to maintain?
  • Which costs continue after the funding period?
  • What assumptions does the business case depend on?
  • What happens if utilization, reimbursement, or another key assumption changes?
  • Are contracts structured with enough flexibility to respond if circumstances change?

A successful launch matters. So does having a realistic plan for what comes afterward.

6. How will you know if the project is getting off track?

Even a strong implementation plan will encounter change.

The goal shouldn't be to anticipate every possible problem. Instead, establish mechanisms for recognizing issues early and addressing them before they threaten the initiative.

Take action

Before launch:

  • Identify your biggest implementation risks.
  • Assign responsibility for monitoring them regularly to catch issues early.
  • Establish regular project checkpoints.
  • Define when and how problems should be escalated.
  • Create a communication structure for internal stakeholders, vendors, funding entities, and other partners.
  • Establish a process for revisiting the plan when circumstances change.

A project plan should guide implementation, not prevent the organization from adapting when new information emerges.

Key takeaways

Moving from funding to implementation requires a shift in thinking and actions. Before launching an RHTP-funded initiative:

Turn the proposal into an executable project plan. Add the details required to manage the actual work.

Keep RHTP outcomes at the center. Connect activities and investments to the goals the project is intended to advance.

Be realistic about capacity. Identify early where internal resources are sufficient and where additional expertise is needed.

Validate dependencies instead of assuming they're ready. Confirm vendor, technology, staffing, and other requirements before establishing your timeline.

Plan for sustainability from the beginning. Understand what happens operationally and financially after the initial funding.

Build in ways to identify and address problems early. Strong governance, communication, and risk management can help keep implementation moving in the right direction.

How BerryDunn can help

Moving a complex initiative from an approved proposal to successful implementation can require expertise and capacity across multiple disciplines.

BerryDunn can help organizations assess implementation readiness, strengthen project and program plans, establish governance and project management structures, identify risks and dependencies, evaluate technology and operational considerations, and plan for long-term sustainability.

Just as importantly, we can help connect those pieces. Large transformation initiatives rarely succeed in silos. Strategy, operations, technology, finance, grants management, and project execution need to work together toward the same outcomes.

Whether you're refining an implementation plan, preparing to launch a funded initiative, or encountering challenges after work has begun, BerryDunn can help you move from funding to action with a practical path forward.

Related Industries

Related Services

Consulting

Related Professionals

Leaders

BerryDunn experts and consultants

Read this if your company is considering outsourced information technology services.

For management, it’s the perennial question: Keep things in-house or outsource?

For management, it’s the perennial question: Keep things in-house or outsource? Most companies or organizations have outsourcing opportunities, from revenue cycle to payment processing to IT security. When deciding whether to outsource, you weigh the trade-offs and benefits by considering variables such as cost, internal expertise, cross coverage, and organizational risk.

In IT services, outsourcing may win out as technology becomes more complex. Maintaining expertise and depth for all the IT components in an environment can be resource-intensive.

Outsourced solutions allow IT teams to shift some of their focus from maintaining infrastructure to getting more value out of existing systems, increasing data analytics, and better linking technology to business objectives. The same can be applied to revenue cycle outsourcing, shifting the focus from getting clean bills out and cash coming in, to looking at the financial health of the organization, analyzing service lines, patient experience, or advancing projects.  

Once you’ve decided, there’s another question you need to ask
Lost sometimes in the discussion of whether to use outsourced services is how. Even after you’ve done your due diligence and chosen a great vendor, you need to stay involved. It can be easy to think, “Vendor XYZ is monitoring our servers or our days in AR, so we should be all set. I can stop worrying at night about our system reliability or our cash flow.” Not true.

You may be outsourcing a component of your technology environment or collections, but you are not outsourcing the accountability for it—from an internal administrative standpoint or (in many cases) from a legal standpoint.

Beware of a false state of confidence
No matter how clear the expectations and rules of engagement with your vendor at the onset of a partnership, circumstances can change—regulatory updates, technology advancements, and old-fashioned vendor neglect. In hiring the vendor, you are accountable for oversight of the partnership. Be actively engaged in the ongoing execution of the services. Also, periodically revisit the contract, make sure the vendor is following all terms, and confirm (with an outside audit, when appropriate) that you are getting the services you need.

Take, for example, server monitoring, which applies to every organization or company, large or small, with data on a server. When a managed service vendor wants to contract with you to provide monitoring services, the vendor’s salesperson will likely assure you that you need not worry about the stability of your server infrastructure, that the monitoring will catch issues before they occur, and that any issues that do arise will be resolved before the end user is impacted. Ideally, this is true, but you need to confirm.

Here’s how to stay involved with your vendor
Ask lots of questions. There’s never a question too small. Here are samples of how precisely you should drill down:

  • What metrics will be monitored, specifically?
  • Why do the metrics being monitored matter to our own business objectives?
  • What thresholds must be met to notify us or produce an alert?
  • What does exceeding a threshold mean to our business?
  • Who on our team will be notified if an alert is warranted?
  • What corrective action will be taken?

Ask uncomfortable questions
Being willing to ask challenging questions of your vendors, even when you are not an expert, is critical. You may feel uncomfortable but asking vendors to explain something to you in terms you understand is very reasonable. They’re the experts; you’re not expected to already understand every detail or you wouldn’t have needed to hire them. It’s their job to explain it to you. Without asking these questions, you may end up with a fairly generic solution that does produce a service or monitor something, but not necessarily all the things you need.

Ask obvious questions
You don’t want anything to slip by simply because you or the vendor took it for granted. It is common to assume that more is being done by a vendor than actually is. By asking even obvious questions, you can avoid this trap. All too often we conduct an IT assessment and are told that a vendor is providing a service, only to discover that the tasks are not happening as expected.

You are accountable for your whole team—in-house and outsourced members
An outsourced solution is an extension of your team. Taking an active and engaged role in an outsourcing partnership remains consistent with your management responsibilities. At the end of the day, management is responsible for achieving business objectives and mission. Regularly check in to make sure that the vendor stays focused on that same mission.

Article
Oxymoron of the month: Outsourced accountability

More and more emphasis is being put on cybersecurity by companies of all sizes. Whether it’s the news headlines of notable IT incidents, greater emphasis on the value of data, or the monetization of certain types of attacks, an increasing amount of energy and money is going towards security. Security has the attention of leadership and the board and it is not going away. One of the biggest risks to and vulnerabilities of any organization’s security continues to be its people. Innovative approaches and new technology can reduce risk but they still don’t prevent the damage that can be inflicted by an employee simply opening an attachment or following a link. This is more likely to happen than you may think.

Technology also doesn’t prepare a management team for how to handle the IT response, communication effort, and workforce management required during and after an event. Technology doesn’t lessen the operational impact that your organization will feel when, not if, you experience an event.

So let’s examine the human and operational side of cybersecurity. Below are three factors you should address to reduce risk and prepare your organization for an event:

  1. People: Create and maintain a vigilant workforce
    Ask yourself, “How prepared is our workforce when it comes to security threats and protecting our data? How likely would it be for one of our team members to click on a link or open an attachment that appear to be from our CFO? Would our team members look closely enough at the email address and notice that the organization name is different by one letter?”
     

    According to the 2016 Verizon Data Breach Report, 30% of phishing messages were opened by the target across all campaigns and 12% went on to click on the attachment or link.

    Phishing email attacks directed at your company through your team range from very obvious to extremely believable. Some attempts are sent widely and are looking for just one person to click, while others are extremely targeted and deliberate. In either case, it is vital that each employee takes enough time to realize that the email request is unusual. Perhaps there are strange typos in the request or it is odd the CFO is emailing while on vacation. That moment your employees take to pause and decide whether to click on the link/attachment could mean the difference between experiencing an event or not.

    So how do you create and cultivate this type of thought process in your workforce? Lots of education and awareness efforts. This goes beyond just an annual in-service training on HIPAA. It may include education sessions, emails with tips and tricks, posters describing the risk, and also exercises to test your workforce against phishing and security exploits. It also takes leadership embracing security as a strategic imperative and leading the organization to take it seriously. Once you have these efforts in place, you can create culture change to build and maintain an environment where an employee is not embarrassed to check with the CFO’s office to see if they really did send an email from Bora Bora.
  1. Plan: Implement a disaster recovery and incident response plan 
    Through the years, disaster recovery plans have been the usual response. Mostly, the emphasis has been on recovering data after a non-security IT event, often discussed in context of a fire, power loss, or hardware failure. Increasingly, cyber-attacks are creeping into the forefront of planning efforts. The challenge with cyber-events is that they are murkier to understand – and harder for leadership – to assist with.

    It’s easier to understand the concept of a fire destroying your server room and the plan entailing acquiring new equipment, recovering data from backup, restoring operations, having good downtime procedures, and communicating the restoration efforts along the way. What is much more challenging is if the event begins with a suspicion by employees, customers, or vendors who believe their data has been stolen without any conclusive information that your company is the originating point of the data loss. How do you take action if you know very little about the situation? What do you communicate if you are not sure what to say? It is this level of uncertainty that makes it so difficult. Do you have a plan in place for how to respond to an incident? Here are some questions to consider:
     
    1. How will we communicate internally with our staff about the incident?
    2. How will we communicate with our clients? Our patients? Our community?
    3. When should we call our insurance company? Our attorney?
    4. Is reception prepared to describe what is going on if someone visits our office?
    5. Do we have the technical expertise to diagnose the issue?
    6. Do we have set protocols in place for when to bring our systems off-line and are our downtime procedures ready to use?
    7. When the press gets wind of the situation, who will communicate with them and what will we share?
    8. If our telephone system and network is taken offline, how we will we communicate with our leadership team and workforce?

By starting to ask these questions, you can ascertain how ready you may, or may not be, for a cyber-attack when it comes.

  1. Practice: Prepare your team with table top exercises  
    Given the complexity and diversity of the threats people are encountering today, no single written plan can account for all of the possible combinations of cyber-attacks. A plan can give guidance, set communication protocols, and structure your approach to your response. But by conducting exercises against hypothetical situations, you can test your plan, identify weaknesses in the plan, and also provide your leadership team with insight and experience – before it counts.

    A table top exercise entails one team member (perhaps from IT or from an outside firm) coming up with a hypothetical situation and a series of facts and clues about the situation that are given to your leadership team over time. Your team then implements the existing plans to respond to the incident and make decisions. There are no right or wrong answers in this scenario. Rather, the goal is to practice the decision-making and response process to determine where improvements are needed.

    Maybe you run an exercise and realize that you have not communicated to your staff that no mention of the event should be shared by employees on social media. Maybe the exercise makes you realize that the network administrator who is on vacation at the time is the only one who knows how to log onto the firewall. You might identify specific gaps that are lacking in your cybersecurity coverage. There is much to learn that can help you prepare for the real thing.

As you know, there are many different threats and risks facing organizations. Some are from inside an organization while others come from outside. Simply throwing additional technology at the problem will not sufficiently address the risks. While your people continue to be one of the biggest threats, they can also be one of your biggest assets, in both preventing issues from occurring and then responding quickly and appropriately when they do. Remember focus on your People, Your Plan, and Your Practice.

Article
The three P's of improving your company's cybersecurity soft skills

Texting has become a simple, convenient, and entrenched component of our everyday lives. We use it with family, friends, coworkers—and clients. My wife and I text to coordinate day care pickup and drop off of our kids every day. It is a quick and easy alternative to our large, and sometimes overwhelming, volume of email.

And with that convenience comes the temptation for clinicians, care teams, and healthcare providers to communicate sensitive content via text in the workplace. The ability to take a photograph of a wound and share with a colleague for a consult is convenient and effective. The number of patients who want to text a non-urgent question to their providers is also growing, particularly with younger patient populations. Population health teams who want to better engage patients may see texting as an easy format to achieve that.

The problem? Texting is not a secure communication method. The native SMS (short message service) used by many phones, including iPhones (at times), is not encrypted, and messages are sent in plain text over cellular networks. SMS messages are vulnerable to “man-in-the-middle” attacks, in which a third-party eavesdrops or potentially manipulates a conversation. The native message format of iPhones has security risks, too. And when a text message contains protected patient information or images, these risks become significant.

On December 28, 2017 CMS released clarification on text messaging. The highlights:

  • Texting is permissible between care team members if accomplished through a secure platform.
  • Texting of orders: prohibited.
  • Computerized Physician Order Entry (CPOE) is the preferred method of provider order entry.

The first bullet allows some consideration of text messaging but with an important caveat: you must use a secure platform. The last two bullets steer providers to using their EHR systems.

What should you do if you find yourself in a position where text messaging has crept into your culture?

  • Establish a policy to govern the use of text messaging and update your mobile device policy.
  • Determine whether you will implement (and allow your care team to use) a secure texting platform or prohibit texting all together.
  • Consider how secure texting impacts your policies and procedures related to data retention, discovery, and the legal health record. 
  • Educate your patients about secure messaging available on your patient portal.
  • Assess your organization’s usage and level of risk.

  • Stop using unsecure text messaging for patient related communications.

For more information, contact me.

Related content:

Watch our video on adopting technology for success. 
Read Dan's article on soft cybersecurity skills.

Article
Texting in healthcare? Best be secure.

There’s a good chance that your organization is in the position of needing to do more with less under the strain of staffing constraints and competing initiatives. With fewer resources to work with, you’ll need to be persuasive to get the green light on new enterprise technology initiatives. To do that, you need to present decision makers with well-thought-out and targeted business cases that show your initiative will have impact and will be successful. Yet developing such a business case is no walk in the park. Perhaps because our firm has its roots in New England, we sometimes compare this process to leading a hiking trip into the woods—into the wild. 

Just as in hiking, success in developing a business case for a new initiative boils down to planning, preparation, and applying a few key concepts we’ve learned from our travels. 

Consensus is critical when planning new technology initiatives

Before you can start the hike, everyone has to agree on some fundamentals: 

Who's going? 

Where are we going? 

When do we go and for how long? 

Getting everyone to agree requires clear communication and, yes, even a little salesmanship: “Trust me. The bears aren’t bad this time of year.” The same principle applies in proposing new technology initiatives; making sure everyone has bought into the basic framework of the initiative is critical to success.

Although many hiking trips involve groups of people similar in age, ability, and whereabouts, for your business initiative you need to communicate with diverse groups of colleagues at every level of the organization. Gaining consensus among people who bring a wide variety of skills and perspectives to the project can be complex.

To gain consensus, consider the intended audiences of your message and target the content to what will work for them. It should provide enough information for executive-level stakeholders to quickly understand the initiative and the path forward. It should give people responsible for implementation or who will provide specific skills substantive information to implement the plan. And remember: one of the most common reasons projects struggle to meet their stated objectives (and why some projects never materialize to begin with), is a lack of sponsorship and buy-in. The goal of a business case is to gain buy-in before project initiation, so your sponsors will actively support the project during implementation. 

Set clear goals for your enterprise technology project 

It’s refreshing to take the first steps, to feel that initial sense of freedom as you set off down the trail. Yet few people truly enjoy wandering around aimlessly in the wilderness for an extended period of time. Hikers need goals, like reaching a mountain peak or seeing famous landmarks, or hiking a predetermined number of miles per day. And having a trail guide is key in meeting those goals. 

For a new initiative, clearly define goals and objectives, as well as pain points your organization wishes to address. This is critical to ensuring that the project’s sponsors and implementation team are all on the same page. Identifying specific benefits of completing your initiative can help people keep their “eyes on the prize” when the project feels like an uphill climb.

Timelines provide additional detail and direction—and demonstrate to decision makers that you have considered multiple facets of the project, including any constraints, resource limitations, or scheduling conflicts. Identifying best practices to incorporate throughout the initiative enhances the value of a business case proposition, and positions the organization for success. By leveraging lessons learned on previous projects, and planning for and mitigating risk, the organization will begin to clear the path for a successful endeavor. 

Don’t compromise on the right equipment

Hiking can be an expensive, time-consuming hobby. While the quality of your equipment and the accuracy of your maps are crucial, you can do things with limited resources if you’re careful. Taking the time to research and purchase the right equipment, (like the right hiking boots), keeps your fun expedition from becoming a tortuous slog. 

Similarly, in developing a business case for a new initiative, you need to make sure that you identify the right resources in the right areas. We all live with resource constraints of one sort or another. The process of identifying resources, particularly for funding and staffing the project, will lead to fewer surprises down the path. As many government employees know all too well, it is better to be thorough in the budget planning process than to return to authorizing sources for additional funding while midstream in a project. 

Consider your possible outcomes

You cannot be too singularly focused in the wild; weather conditions change quickly, unexpected opportunities reveal themselves, and being able to adapt quickly is absolutely necessary in order for everyone to come home safely. Sometimes, you should take the trail less traveled, rest in the random lean-to that you and your group stumble upon, or go for a refreshing dip in a lake. By focusing on more than just one single objective, it often leads to more enjoyable, safe, and successful excursions.

This type of outlook is necessary to build a business case for a new initiative. You may need to step back during your initial planning and consider the full impact of the process, including on those outside your organization. For example, you may begin to identify ways in which the initiative could benefit both internal and external stakeholders, and plan to move forward in a slightly new direction. Let’s say you’re building a business case for a new land management and permitting software system. Take time to consider that this system may benefit citizens, contractors, and other organizations that interact with your department. This new perspective can help you strengthen your business case. 

Expect teamwork

A group that doesn’t practice teamwork won’t last long in the wild. In order to facilitate and promote teamwork, it’s important to recognize the skills and contributions of each and every person. Some have a better sense of direction, while some can more easily start campfires. And if you find yourself fortunate enough to be joined by a truly experienced hiker, make sure that you listen to what they have to say.

Doing the hard work to present a business case for a new initiative may feel like a solitary action at times, but it’s not. Most likely, there are other people in your organization who see the value in the initiative. Recognize and utilize their skills in your planning. We also suggest working with an experienced advisor who can leverage best practices and lessons learned from similar projects. Their experience will help you anticipate potential resistance and develop and articulate the mitigation strategies necessary to gain support for your initiative.

If you have thoughts, concerns, or questions, contact our team. We love to discuss the potential and pitfalls of new initiatives, and can help prepare you to head out into the wild. We’d love to hear any parallels with hiking and wilderness adventuring that you have as well. Let us know! 

BerryDunn’s local government consulting team has the experience to lead technology planning initiatives and develop actionable plans that help you think strategically and improve service delivery. We partner with you, maintaining flexibility and open lines of communication to help ensure that your team has the resources it needs.

Our team has broad and deep experience partnering with local government clients across the country to modernize technology-based business transformation projects and the decision-making and planning efforts. Our expertise includes software system assessments/planning/procurement and implementation project management; operational, management, and staffing assessments; information security; cost allocation studies; and data management.  

Article
Into the wild: Building a business case for a new enterprise technology project

Read this if your organization is planning on upgrading or replacing an enterprise technology system.

It can be challenging and stressful to plan for technology initiatives, especially those that involve and impact every area of your organization. Common initiatives include software upgrades or replacements for:

  • Financial management, such as Enterprise Resource Planning (ERP) systems
  • Asset management systems
  • Electronic health records (EHR) systems
  • Permitting and inspections systems

Though the number of considerations when planning enterprise technology projects can be daunting, the greatest mistake you can make is not planning at all. By addressing just a few key areas, you can avoid some of the most common pitfalls, such as exceeding budget and schedule targets, experiencing scope creep, and losing buy-in among stakeholders. Here are some tips to help you navigate your next project:

Identify your IT project roles and resources

While most organizations understand the importance of identifying project stakeholder groups, it is often an afterthought. Defining these roles at the outset of your project helps you accurately estimate the work effort.

Your stakeholder groups may include:

  • An executive sponsor
  • A steering committee
  • A project manager
  • Functional leads
  • A technical team

Once you’ve established the necessary roles, you can begin reviewing your organization’s resources to determine the people who will be available to fill them. Planning for resource availability will help you avoid delays, minimize impact to regular business processes, and reduce the likelihood of burnout. But this plan won’t remain static—you can expect to make updates throughout the project.

Establish clear goals and objectives to keep your technology project on track

It’s important that an enterprise technology project has established goals and objectives statements. These statements will help inform decision-making, provide benchmarks for progress, and measure your project’s success. They can then be referenced when key stakeholders have differing perspectives on the direction to take with a pending decision. For example, if the objective of your project is to reduce paper-based processes, you may plan for additional computer workstations and focus technical resources on provisioning them. You’ll also be able to measure your success in the reduction of paper-based tasks.

Estimate your IT project budget accurately

Project funding is hardly ever overlooked, but can be complex with project budgets that are either underestimated or estimated without sufficient rationale to withstand approval processes and subsequent budget analysis. You may find that breaking down estimates to a lower level of detail helps address these challenges. Most technology projects incur costs in three key areas:

  • Vendor cost: This could include both one-time software implementation costs as well as recurring costs for maintenance and ongoing support.
  • Infrastructure cost: Consider the cost of any investments needed to support your project, such as data center hardware, networking components, or computing devices.
  • Supplemental resource cost: Don’t forget to include the cost of any additional resources needed for their specialized knowledge or to simply backfill project staff. This could include contracted resources or the additional cost of existing resources (i.e., overtime).

A good technology project budget also includes a contingency amount. This amount will depend on your organization’s standards, the relative level of confidence in your estimates, and the relative risk.

Anticipate the need for change management

Depending on the project, staff in many areas of your organization will be impacted by some level of change during a technology implementation. External stakeholders, such as vendors and the public, may also be affected. You can effectively manage this change by proactively identifying areas of likely change resistance and creating strategies to address them.

In any technology implementation, you will encounter change resistance you did not predict. Having strategies in place will help you react quickly and effectively. Some proven change management strategies include communicating throughout your project, involving stakeholders to get their buy-in, and helping ensure management has the right amount of information to share with their employees.

Maintain focus and stay flexible as you manage your IT project

Even with the most thought-out planning, unforeseen events and external factors may impact your technology project. Establish mechanisms to regularly and proactively monitor project status so that you can address material risks and issues before their impact to the project grows. Reacting to these items as they arise requires key project stakeholders to be flexible. Key stakeholders must recognize that new information does not necessarily mean previous decisions were made in error, and that it is better to adapt than to stick to the initial direction.

Whether you’re implementing an ERP, an EHR, or enterprise human resources or asset management systems, any enterprise technology project is a massive undertaking, involving significant investment and a coordinated effort with individuals across multiple areas of an organization. Common mistakes can be costly, but having a structured approach to your planning can help avoid pitfalls. Our experienced, objective advisors have worked with public and private organizations across the country to oversee large enterprise projects from inception to successful completion.

Contact our software consulting team with any questions.

Article
Planning for a successful enterprise technology project

Read this if you are a State Medicaid Director, State Medicaid Chief Information Officer, State Medicaid Project Manager, or State Procurement Officer—or if you work on a State Medicaid Enterprise System (MES) certification effort.

On October 24, 2019, the Centers for Medicaid and Medicare Services (CMS) published the Outcomes-Based Certification (OBC) guidance for the Electronic Visit Verification (EVV) module. Now, CMS is looking to bring the OBC process to the rest of the Medicaid Enterprise. 

The shift from a technical-focused certification to a business outcome-focused approach presents a unique opportunity for states as they begin re-procuring—and certifying—their Medicaid Enterprise Systems (MES).

Once you have defined the scope of your MES project—and know you need to undertake CMS certification—you need to ask “what’s next?” OBC can be a more efficient certification process to secure Federal Financial Participation (FFP).

What does OBC certification entail?

Rethinking certification in terms of business outcomes will require agencies to engage business and operations units at the earliest possible point of the project development process to define the program goals and define what a successful implementation is. One way to achieve this is to consider MES projects in three steps. 

Three steps to OBC evaluation

Step 1: Define outcomes

The first step in OBC planning seems easy enough: define outcomes. But what is an outcome? To answer that, it’s important to understand what an outcome isn’t. An outcome isn’t an activity. Instead, an outcome is the result of the activity. For example, the activity could be procuring an EVV solution. In this instance, an outcome could be that the state has increased the ability to detect fraud, waste, and abuse through increased visibility into the EVV solution.

Step 2: Determine measurements

The second step in the OBC process is to determine what to measure and how exactly you will measure it. Deciding what metrics will accurately capture progress toward the new outcomes may be intuitive and therefore easy to define. For example, a measure might simply be that each visit is captured within the EVV solution.

Increasing the ability to detect fraud, waste, and abuse could simply be measured by the number of cases referred to a Medicaid fraud unit or dollars recovered. However, you may not be able to easily measure that in the short-term. Instead, you may need to determine its measurement in terms of an intermediate goal, like increasing the number of claims checked against new data as a result of the new EVV solution. By increasing the number of checked claims, states can ensure that claims are not being paid for unverified visits. 

Step 3: Frequency and reporting

Finally, the state will need to determine how often to report to measure success. States will need to consider the nuances of their own Medicaid programs and how those nuances fit into CMS’ expectations, including what data is available at what intervals.

OBC represents a fundamental change to the certification process, but it’s important to highlight that OBC isn’t completely unfamiliar territory. There is likely to be some carry-over from the certification process as described in the Medicaid Enterprise Certification Toolkit (MECT) version 2.3. The current Medicaid Enterprise Certification (MEC) checklists serve as the foundation for a more abbreviated set of criteria. New evaluation criteria will look and feel like the criteria of old but are likely to be a fraction of the 741 criteria present in the MECT version 2.3.

OBC offers several benefits to states as you navigate federal certification requirements:

  1. You will experience a reduction in the amount of time, effort, and resources necessary to undertake the certification process. 
  2. OBC refocuses procurement in terms of enhancements to the program, not in new functions. Consequently, states will also be able to demonstrate the benefits that each module brings to the program which can be integral to stakeholder support of each module. 
  3. Early adoption of the OBC process can allow you to play a more proactive role in certification efforts.

Continue to check back for a series of our project case studies. Additionally, if you are considering an OBC effort and have questions, please contact our team. You can read the OBC guidance on the CMS website here. 
 

Article
Three steps to outcomes-based certification

As the Project Management Body of Knowledge® (PMBOK®) explains, organizations fall along a structure and reporting spectrum. On one end of this spectrum are functional organizations, in which people report to their functional managers. (For example, Finance staff report to a Finance director.) On the other end of this spectrum are projectized organizations, in which people report to a project manager. Toward the middle of the spectrum lie hybrid—or matrix—organizations, in which reporting lines are fairly complex; e.g., people may report to both functional managers and project managers. 

Problem: Weak Matrix Medicaid System Vendors

This brings us to weak matrix organizations, in which functional managers have more authority than project managers. Many Medicaid system vendors happen to fall into the weak matrix category, for a number of different reasons. Yet the primary factor is the volume and duration of operational work—such as provider enrollment, claims processing, and member enrollment—that Medicaid system vendors perform once they exit the design, development, and implementation (DDI) phase.

This work spans functional areas, which can muddy the reporting waters. Without strong and clear reporting lines to project managers, project success can be seriously (and negatively) affected if the priorities of the functional leads are not aligned with those of the project. And when a weak matrix Medicaid system vendor enters a multi-vendor environment in which it is tasked with implementing a system that will serve multiple departments and bureaus within a state government, the reporting waters can become even muddier.


Solution: Using a Project Management Office (PMO) Vendor

Conversely, consulting firms that provide Project Management Office (PMO) services to government agencies tend to be strong matrix organizations, in which project managers have more authority over project teams and can quickly reallocate team members to address the myriad of issues that arise on complex, multi-year projects to help ensure project success. PMOs are also typically experienced at creating and running project governance structures and can add significant value in system implementation-related work across government agencies.

Additional benefits of a utilizing a PMO vendor include consistent, centralized reporting across your portfolio of projects and the ability to quickly onboard subject matter expertise to meet program and project needs. 
For more in-depth information on the benefits of using a PMO on state Medicaid projects, stay tuned for my second blog in this series. In the meantime, feel free to send your PMO- or Medicaid-related questions to me. 
 

Article
The power of the PMO: Fixing the weak matrix